You have studied members one at a time: a plate in tension, a column, a beam, a footing. A real project does not announce which member it is. It hands you a floor plan, a set of loads and a soil report, and expects you to decide what to check and in what order. This closing chapter is practice at exactly that.

Five steps from loads to details with an iteration arrow
Caption: The same five steps apply to a steel beam, a concrete beam or a footing. The skill is knowing how to run them quickly and check your own work.

What you will learn

  • The five-step workflow used in every project.
  • How to estimate sizes by hand before using any software.
  • How to sanity-check an answer.
  • What the lessons of this chapter contain.

Key terms

Tributary area: the part of a floor whose load is carried by one member.

Demand-capacity ratio: factored demand divided by design capacity; the design is acceptable if it is at most 1.

Preliminary design: a quick first sizing, refined by detailed checks.

Sanity check: a rough independent calculation confirming that an answer is the right size.

The five steps

  1. Loads. Dead load (self-weight, finishes, partitions), live load from the building use, and wind, snow or earthquake as needed. Combine them with the code factors, for example 1.2D + 1.6L.
  2. Analysis. Find the shear, moment, axial force and deflection in each member. For a simply supported beam, Mu = wLยฒ/8, Vu = wL/2.
  3. Member selection. Choose a size from rules of thumb: beam depth about span/20 for steel and span/12 to span/16 for concrete, column area from P/(0.5 Fy) to start.
  4. Checks. Strength limit states first (flexure, shear, buckling), then serviceability (deflection, drift, crack width, settlement).
  5. Details. Connections, bar anchorage, bracing, cover. Many structural failures come from details that were never drawn.

If a check fails, you change the member and go around the loop again. Iteration is normal; you are looking for the lightest or cheapest member whose demand-capacity ratio is just under 1.

How to check your own work

  • Order of magnitude. A 6 m office floor beam at 3 m spacing carries something like 25 to 35 kN/m. A result of 3 or 300 kN/m should stop you.
  • Units. Convert everything to N and mm (or kN and m) before calculating. Most large errors are unit errors.
  • Independent estimate. The elastic moment M = ฯƒ S should land near the same result as the plastic one with a 12 percent difference, not 50 percent.
  • Equilibrium. The reactions must sum to the total applied load.

What this chapter contains

Project routine

List the loads With units
Compute demands M, V, P, deflection
Check capacity Every limit state
Detail it So it can be built

Repeat until ratios are below 1

1 / 2

Try it

Python Load takedown: from floor pressure to column load

Press Run (or Ctrl + Enter) to see the result here.

Program input ยท what you'd type while the program runs

Type the answers before you press Run, one per line. Each time the program reads a line (with input()), it gets the next line from this box.

Interactive: tributary width to line load

Check your understanding

Quick check ยท 4 questions

of 4 answered You scored / 4 ยท perfect!

  1. 1. What is the tributary area of a member?

    Load on a floor is assigned to the members that support that part of the floor.
  2. 2. A design is acceptable if the demand-capacity ratio is

    Demand must not exceed capacity.
  3. 3. What should you do first when a check fails?

    Iterate: strengthen or resize and run the checks again.
  4. 4. Which is a good sanity check on a beam moment?

    Simple formulas give a quick independent estimate.

Summary

  • Every project follows loads, analysis, member selection, checks, details, with iteration.
  • Tributary width converts a floor pressure into a line load on a beam.
  • Always check units, equilibrium and order of magnitude.