Bài 15 · Surveying and Mapping

Chapter 3 Review: Surveying and Mapping

Review surveying: scale and contours, slope reduction and tape corrections, azimuths, leveling, traverse misclosure, adjustment and area, with a ten-question quiz.

Surveying turns a messy landscape into numbers you can trust. This chapter taught you the four building blocks: distance, direction, height and position. Each comes with a check, so you know when to believe your numbers. Use this page to review the checks and try a combined calculator.

Four summary cards for distance, direction, height and position with a bottom banner about checking closures
Chapter 3 in one picture: reduce distances, carry azimuths, level heights and close the traverse.

Recap table

Lesson Big idea Key formulas
Chapter 3 Overview Datums, scale, contours, error types Ground = map × scale; slope = interval ÷ distance
Measuring Distances and Angles Reduce and correct distances; azimuth and bearing H = S cos θ, Ct = α (T − T0) S, sag −w²L³/(24P²)
Leveling and Elevations Height difference from staff readings HI = RL + BS, RL = HI − FS, ΣBS − ΣFS = ΔRL
Traverse, Coordinates and Area Latitude, departure, misclosure, Bowditch, area ΔN = L cos Az, ΔE = L sin Az, precision 1 : P/c

Try it

Python Quick surveying toolkit

Press Run (or Ctrl + Enter) to see the result here.

Program input · what you'd type while the program runs

Type the answers before you press Run, one per line. Each time the program reads a line (with input()), it gets the next line from this box.

JS Accuracy of your tape

Press Run (or Ctrl + Enter) to see the console output here.

No output.

Check your understanding

Quick check · 10 questions

of 10 answered You scored / 10 · perfect!

  1. 1. On a map at 1:5,000, a road measures 3.6 cm. How long is it on the ground?

    3.6 cm × 5,000 = 18,000 cm = 180 m.
  2. 2. A slope distance of 60.00 m is measured at 12° (cos 12° = 0.9781). H = ?

    H = 60.00 × 0.9781 = 58.69 m.
  3. 3. Which correction is always negative?

    Sag pulls the tape ends together, so the true distance is shorter than the reading.
  4. 4. What is the bearing for azimuth 300°?

    300° is in the north-west quadrant, 360° − 300° = 60° from north: N 60° W.
  5. 5. BM = 75.000 m, BS = 2.000 m, FS = 1.250 m on a new point. Its RL is:

    HI = 77.000, RL = 77.000 − 1.250 = 75.750 m.
  6. 6. A bigger staff reading means the point is:

    The reading is measured down from the line of sight, so a bigger reading means a lower point.
  7. 7. Why keep backsight and foresight distances equal?

    Distance-dependent errors affect both sights equally and cancel in the difference.
  8. 8. A traverse has c = 0.20 m and perimeter 1,000 m. Its precision is:

    P/c = 1,000 / 0.20 = 5,000.
  9. 9. In the Bowditch rule the correction to each line depends on:

    Correction = −(sum of error) × (L / P).
  10. 10. The interior angles of a six-sided closed traverse should sum to:

    (6 − 2) × 180° = 720°.

Summary

  • Maps rely on scale, datums and contours; blunders, systematic and random errors need different cures.
  • Reduce slope distances and correct tapes; carry azimuths with back azimuth + angle right.
  • Leveling uses HI = RL + BS and RL = HI − FS, with arithmetic and closing checks.
  • Traverses are checked by misclosure and precision, adjusted by Bowditch and turned into coordinates and area.
  • Chapter 4 turns to the materials that engineers measure, specify and build with.

Next: Chapter 4 Overview: Construction Materials

Theo dõi tiến độ của bạn

Tạo tài khoản miễn phí để đánh dấu bài đã học và tiếp tục từ chỗ bạn dừng lại trên mọi thiết bị.