Stakeholders: Identification and Analysis

Learn who project stakeholders are, how to identify and classify them, how to use the power-interest grid and a stakeholder register to plan engagement for each group.

A stakeholder is any person, group or organization that can affect the project or is affected by it. That includes the sponsor and the team, but also customers, end users, regulators, suppliers, neighbouring departments, and sometimes people who simply dislike the change. Many project failures are stakeholder failures: a powerful person was surprised late, or the people who would use the product were never asked.

Types of stakeholders

  • Internal: sponsor, executives, project team, functional managers, other departments.
  • External: customers, end users, suppliers and vendors, regulators, partners, the public or local community.
  • Primary (directly involved or affected) and secondary (indirectly affected).
  • Supportive, neutral or resistant: their attitude to the project.

Stakeholders also differ by what they care about: finance cares about cost, operations about stability, users about ease of use, legal about compliance.

Step 1: identify

Identify stakeholders early, in initiation, and keep revisiting the list. Ways to find them:

  • Read the business case and charter.
  • Interview the sponsor: "Who else will care about this?"
  • Walk the process the project changes and list everyone who touches it.
  • Review similar past projects.
  • Ask each stakeholder who else you should talk to.

Step 2: analyse

For each stakeholder, record:

  • Power: ability to affect the project (money, authority, veto).
  • Interest: how much they are affected or care.
  • Influence over other stakeholders.
  • Attitude now and desired attitude.
  • Needs and expectations.

The power-interest grid

Plotting power against interest suggests how to engage each person.

Low interest High interest
High power Keep satisfied: brief them, avoid surprises Manage closely: involve in decisions, frequent talks
Low power Monitor: minimal effort, watch for change Keep informed: regular updates, listen to feedback
quadrantChart
    title Power versus interest
    x-axis Low interest --> High interest
    y-axis Low power --> High power
    quadrant-1 Manage closely
    quadrant-2 Keep satisfied
    quadrant-3 Monitor
    quadrant-4 Keep informed
    Sponsor: [0.9, 0.9]
    Legal: [0.3, 0.8]
    End users: [0.85, 0.3]
    Neighbouring team: [0.2, 0.2]

Example placements. Yours will differ; re-plot as the project changes.

Python Classify stakeholders on the grid

Press Run (or Ctrl + Enter) to see the result here.

Program input ยท what you'd type while the program runs

Type the answers before you press Run, one per line. Each time the program reads a line (with input()), it gets the next line from this box.

Step 3: plan engagement

The stakeholder engagement plan states, for each important stakeholder, the current and desired level of involvement:

  • Unaware: does not know about the project.
  • Resistant: knows, opposes.
  • Neutral: knows, neither supports nor opposes.
  • Supportive: supports the change.
  • Leading: actively drives success.

The gap between current and desired level tells you where to spend your time.

Python Engagement gaps

Press Run (or Ctrl + Enter) to see the result here.

Program input ยท what you'd type while the program runs

Type the answers before you press Run, one per line. Each time the program reads a line (with input()), it gets the next line from this box.

The stakeholder register

A stakeholder register is the living document that stores all of this: name, role, contact, requirements, influence, attitude, engagement strategy and owner of the relationship. Keep sensitive comments (such as "resistant") careful: assume the register could be read by anyone.

Engaging well

  • Talk early and listen more than you present.
  • Translate: executives need outcomes and risk; engineers need detail.
  • Agree how and how often each group is contacted (see the project plan).
  • Turn resistance into information: ask what they fear losing.
  • Update the register at every phase gate, and whenever someone new appears.

Positive stakeholders are not "free". Over-involving supporters costs time; under-involving them wastes goodwill.

Check your understanding

Quick check ยท 4 questions

of 4 answered You scored / 4 ยท perfect!

  1. 1. A stakeholder has high power and low interest. According to the grid, you should...

    High power but low interest: brief them enough to keep them satisfied.
  2. 2. When should stakeholders be identified?

    New stakeholders appear over time, so the list is kept up to date.
  3. 3. What does the engagement plan compare?

    The gap shows who needs the most attention.
  4. 4. End users with low power but high interest should be...

    They care a lot and know the work; keep them informed and use their feedback.

Summary

  • A stakeholder is anyone who affects or is affected by the project.
  • Identify early, analyse power, interest, attitude and needs, then plan engagement.
  • The power-interest grid suggests manage closely, keep satisfied, keep informed or monitor.
  • Keep a stakeholder register and update it throughout.