Business Case and Project Charter

Learn why companies execute projects, how to write a business case with cost-benefit analysis (NPV, ROI, payback) and how a project charter authorizes the work.

Projects do not start because someone has a clever idea. They start because an organization decides the expected benefit is worth the cost. The documents that capture that decision are the business case, which argues why the project should exist, and the project charter, which formally authorizes it and names who runs it. Getting these right is the cheapest way to avoid building the wrong thing.

Why do organizations run projects?

Almost every project responds to one of these drivers.

  • Strategy: to reach a goal such as entering a new market.
  • Market demand: customers want a new product or feature.
  • Regulation or legal need: new data-protection rules, safety standards.
  • Problem or opportunity: an old system is failing, or a new technology makes something possible.
  • Efficiency: reduce cost, automate manual work, improve quality.
  • Stakeholder request: a customer, department or executive asks for it.

Each driver should translate into a measurable benefit. "Modernize the system" is vague; "cut order-processing time from 6 minutes to 2 and save 400 staff hours a month" is something you can approve and later check.

The business case

A business case is a short document (or a section in a larger one) that answers:

  1. Problem or opportunity: what is wrong or possible?
  2. Options: doing nothing, option A, option B, with pros and cons.
  3. Benefits: financial and non-financial, with how they will be measured.
  4. Costs: build, run, training, and hidden costs.
  5. Risks and assumptions.
  6. Recommendation and success criteria.

Always include "do nothing" as an option. It is the baseline all others are compared to.

Financial measures

Three simple measures dominate business cases.

  • ROI (return on investment): (total benefits - total costs) / total costs.
  • Payback period: how long until accumulated benefits cover the cost.
  • NPV (net present value): the sum of future cash flows discounted to today's value, because money later is worth less than money now. A positive NPV means the project creates value at the chosen discount rate.
Python ROI, payback and NPV

Press Run (or Ctrl + Enter) to see the result here.

Program input ยท what you'd type while the program runs

Type the answers before you press Run, one per line. Each time the program reads a line (with input()), it gets the next line from this box.

Comparing options

Python Compare options by NPV

Press Run (or Ctrl + Enter) to see the result here.

Program input ยท what you'd type while the program runs

Type the answers before you press Run, one per line. Each time the program reads a line (with input()), it gets the next line from this box.

NPV is only as good as its inputs. Test the case with pessimistic numbers too. Non-financial benefits (safety, reputation, compliance) can justify a project with low financial return, but state them plainly.

The project charter

Once the sponsor agrees, a project charter formally authorizes the project and gives the project manager authority to use resources. It is usually short (one to three pages) and typically contains:

Section Content
Purpose and justification Link to the business case
Objectives and success criteria Measurable targets
High-level scope and deliverables What is in; what is out
Summary milestones Key dates
Summary budget Approved funding level
Key risks and assumptions Known at start
Stakeholders Sponsor, customers, key groups
Project manager and authority level Who decides what
Approval Signatures and date
flowchart LR
    A[Idea or need] --> B[Business case]
    B --> C{Approved?}
    C -- No --> D[Stop or rethink]
    C -- Yes --> E[Project charter]
    E --> F[Planning begins]

Charter approval marks the formal start of the project.

Good objectives: SMART

Write objectives that are Specific, Measurable, Achievable, Relevant and Time-bound. Compare:

  • Weak: "Improve the website."
  • Strong: "Reduce checkout abandonment from 70% to 55% within six months of launch."
Python Check an objective for measurability

Press Run (or Ctrl + Enter) to see the result here.

Program input ยท what you'd type while the program runs

Type the answers before you press Run, one per line. Each time the program reads a line (with input()), it gets the next line from this box.

Common mistakes

  • Starting without a sponsor who can say yes and pay.
  • Benefits so vague they cannot be checked later.
  • Ignoring operating costs after delivery.
  • Treating the charter as a formality and never reading it again; it is your reference when scope arguments appear.

Check your understanding

Quick check ยท 4 questions

of 4 answered You scored / 4 ยท perfect!

  1. 1. What does a business case primarily explain?

    The business case justifies the project and compares options.
  2. 2. A positive NPV means...

    Discounted benefits exceed the costs.
  3. 3. What does the project charter do?

    The charter formally starts the project and names the project manager.
  4. 4. Why include a 'do nothing' option?

    Without the baseline you cannot judge the value of acting.

Summary

  • Projects start to serve strategy, demand, regulation, efficiency or problems.
  • A business case compares options with costs, benefits, ROI, payback and NPV.
  • The charter authorizes the project, names the manager and states objectives and high-level scope.
  • Write SMART objectives so success can be checked.