Lesson 41 of 41 ยท Projects and Practice

Practice Problems and Certifications

Practice project management calculations (PERT, critical path, EVM, communication channels), see how to prepare for PMP, PRINCE2, CAPM and Scrum exams, and pick a career path.

This final lesson lets you test yourself, prepares you for professional exams and shows where a project management career can go. First, a set of calculation problems, since formulas are the part most people forget. Then, a guide to the main certifications and a study plan.

Formula sheet

Topic Formula
PERT expected duration (O + 4M + P) / 6
PERT standard deviation (P - O) / 6
Communication channels n(n - 1) / 2
EMV probability x impact
SV, CV EV - PV, EV - AC
SPI, CPI EV / PV, EV / AC
EAC (typical) BAC / CPI
ETC, VAC EAC - AC, BAC - EAC
TCPI to BAC (BAC - EV) / (BAC - AC)
Float LS - ES (or LF - EF)
Little's Law cycle time = WIP / throughput
ROI (benefit - cost) / cost
Payback period cost / periodic benefit

Try the problems on paper first, then run the checker. All answers are in the code at the end of each section.

Problem set 1: estimating and communication

  1. A task has O = 6, M = 9, P = 18 days. What are its PERT mean and standard deviation?
  2. A team grows from 8 to 15. How many new communication channels are created?
  3. Three risks: 30 percent chance of a 20,000 loss; 10 percent of 50,000; 50 percent of 6,000. What is the contingency?
Python Check problem set 1

Press Run (or Ctrl + Enter) to see the result here.

Program input ยท what you'd type while the program runs

Type the answers before you press Run, one per line. Each time the program reads a line (with input()), it gets the next line from this box.

Problem set 2: earned value

A project has BAC = 400,000. At the status date: PV = 160,000, EV = 140,000, AC = 175,000.

  1. SV, CV, SPI, CPI?
  2. EAC if the cost trend continues? ETC? VAC?
  3. Is finishing within the BAC realistic? (TCPI.)
  4. What if the overrun is a one-time event and the rest will go to plan? (EAC = AC + BAC - EV.)
Python Check problem set 2

Press Run (or Ctrl + Enter) to see the result here.

Program input ยท what you'd type while the program runs

Type the answers before you press Run, one per line. Each time the program reads a line (with input()), it gets the next line from this box.

Problem set 3: critical path

Activities (days, predecessors): A 3 (none), B 4 (A), C 2 (A), D 5 (B, C), E 3 (C), F 2 (D, E). Find the project duration, the critical path and the float of C and E.

Python Check problem set 3

Press Run (or Ctrl + Enter) to see the result here.

Program input ยท what you'd type while the program runs

Type the answers before you press Run, one per line. Each time the program reads a line (with input()), it gets the next line from this box.

Problem set 4: agile and flow

  1. Velocity of the last 4 sprints: 18, 22, 20, 24. The backlog has 150 points. How many sprints at the average?
  2. A Kanban team has 18 items in progress and finishes 6 per week. Average cycle time? What happens if WIP is cut to 9 with the same throughput?
  3. Investment 80,000 returns 30,000 each year. Payback and ROI after 4 years?
Python Check problem set 4

Press Run (or Ctrl + Enter) to see the result here.

Program input ยท what you'd type while the program runs

Type the answers before you press Run, one per line. Each time the program reads a line (with input()), it gets the next line from this box.

Scenario practice

Certification exams use situational questions. Think about what you would do first.

  • A team member tells you privately that a deliverable is far behind. Assess the facts, check the impact on the critical path, and update the plan and the risk log before going to the sponsor with options.
  • A stakeholder asks for a new feature mid-sprint. Ask the product owner to place it in the backlog and consider swapping, not adding.
  • Two senior engineers disagree on the architecture. Facilitate: get the criteria, evidence and risks; if no consensus, escalate for a decision with the data.
  • The sponsor wants a date you know is unrealistic. Show a range with confidence levels and options (scope, resources, date).

The common pattern: gather facts, analyze impact, follow the agreed process, communicate early, and bring options.

Professional certifications

Certification Body Best for Notes
CAPM PMI Beginners Entry-level exam on fundamentals
PMP PMI Experienced project managers Predictive, agile and hybrid; requires experience
PRINCE2 Foundation and Practitioner Axelos / PeopleCert Public sector, UK and Europe Process and governance
PMI-ACP PMI Agile practitioners Agile approaches in general
PSM and PSPO Scrum.org Scrum Masters and Product Owners Based on the Scrum Guide
CSM and CSPO Scrum Alliance Scrum roles Course-based
SAFe certifications Scaled Agile Large agile programs SAFe framework
Six Sigma Green and Black Belt Various Quality and process improvement DMAIC
ITIL Axelos IT service management Service-oriented

Exam details, fees and prerequisites change, so check the current official site before you plan. Employers value certifications, but they care more about delivered projects.

How to prepare

  1. Learn the structure: read the exam content outline, so you know the domains and their weights.
  2. Use one main source (the official guide) and one question bank.
  3. Understand, don't memorize. Formulas matter, but most questions are situational.
  4. Practice timed question sets, review every wrong answer and write down why the right answer is right.
  5. Study in short daily sessions over 6 to 10 weeks.
  6. Simulate the exam at least twice, including the time limit.

Building a career

  • Entry: project coordinator, assistant PM, junior business analyst, Scrum team member.
  • Mid: project manager, Scrum Master, product owner, delivery manager.
  • Senior: program manager (a group of related projects), portfolio manager (strategic selection of investments), PMO director, head of delivery.

Skills that set people apart: clear writing, honest estimates, comfortable conversations about money, domain knowledge (software, construction, health), basic data skills (the Python in this course is a start; spreadsheets and SQL go far too), and calm in a crisis.

What next

You have covered the lifecycle from initiation to closure, the schedule and cost techniques, risk and quality, agile methods, tools and leadership. To keep growing:

  • Run a real project, even a small one: a family trip, a charity event, a feature at work. Use a plan, a risk list, a status report and a lessons-learned session.
  • Join a local or online project management community and read case studies of failures.
  • Learn one tool deeply (see project management tools).
  • Redo the capstone with a project from your own life.

Check your understanding

Quick check ยท 4 questions

of 4 answered You scored / 4 ยท perfect!

  1. 1. BAC = 100,000, EV = 40,000, AC = 50,000. What is CPI?

    CPI = EV / AC = 40,000 / 50,000 = 0.80.
  2. 2. Which certification is based on the Scrum Guide and aimed at Scrum Masters?

    Professional Scrum Master (PSM) from Scrum.org follows the Scrum Guide.
  3. 3. In a situational exam question, what is usually the best first move when a problem arises?

    Assess first, then follow the agreed process and bring options when you escalate.
  4. 4. A program manager differs from a project manager because they:

    Programs coordinate related projects to deliver benefits that individual projects could not.

Summary

  • Memorize the key formulas, but practice applying them in scenarios.
  • Calculations to master: PERT, communication channels, EMV, earned value, critical path, Little's Law, ROI and payback.
  • Certifications (CAPM, PMP, PRINCE2, Scrum.org, SAFe, ITIL) suit different roles; check current requirements.
  • Prepare with the exam outline, one main source, timed practice and a review of mistakes.
  • Experience beats credentials: run real projects and write down your lessons.