Lesson 37 of 41 ยท Leadership and Stakeholders

Stakeholder Management

Identify and engage project stakeholders: types, the power-interest grid, salience, the stakeholder register, engagement levels and RACI matrices, with runnable Python.

A stakeholder is any person, group or organization that can affect the project or be affected by it. Sponsors, customers, end users, your own team, suppliers, regulators, neighbors of a building site and even competitors can all be stakeholders. Projects rarely fail for lack of technical skill alone; they fail because a powerful person was ignored, a user group was never consulted or a rumor went unanswered.

Stakeholder management is the continuing process of finding these people, understanding what they want, and engaging them in the right way.

Types of stakeholders

  • Internal: sponsor, steering committee, project team, functional managers, other projects.
  • External: customers, end users, suppliers and contractors, regulators, partners, the public, the media.
  • Primary (directly affected, such as users) and secondary (indirectly affected, such as support staff).
  • Supporters, neutrals and resistors. The resistors need the most attention, not the least.

Key roles: the sponsor (provides money and authority, removes organizational obstacles, signs off), the customer (accepts the result), the end users (live with it), and the project team.

The process

Four stakeholder steps

Identify Find everyone affected, early.
Analyze Power, interest, attitude, needs.
Plan Choose engagement and messages.
Engage and monitor Act, listen, update the register.

Re-do it at every phase; stakeholders change.

1 / 2

Identify with workshops, org charts, contract lists and the question "who else?" at the end of every meeting. Record each in a stakeholder register: name, role, contact, interests, expectations, influence, current and desired attitude, engagement strategy and owner.

The power-interest grid

The classic way to prioritize is a two-by-two grid of power (ability to influence the project) and interest (how much the project concerns them).

Low interest High interest
High power Keep satisfied Manage closely
Low power Monitor Keep informed
  • Manage closely: sponsor, key customer. Frequent two-way contact, involve in decisions.
  • Keep satisfied: a senior executive who is not involved. Brief updates; avoid surprises.
  • Keep informed: end users. Regular updates, ways to give feedback.
  • Monitor: minimal effort, watch for changes.
Python Classify stakeholders on the power-interest grid

Press Run (or Ctrl + Enter) to see the result here.

Program input ยท what you'd type while the program runs

Type the answers before you press Run, one per line. Each time the program reads a line (with input()), it gets the next line from this box.

Other models add detail: the salience model (power, legitimacy, urgency), the influence-impact grid, and the stakeholder cube with three dimensions. For most projects the two-by-two grid is enough, as long as you review it regularly.

Engagement levels

Compare where each stakeholder is with where you need them to be, using the stakeholder engagement assessment matrix:

Level Description
Unaware Does not know about the project
Resistant Aware, opposes change
Neutral Aware, neither supports nor opposes
Supportive Aware, supports change
Leading Actively engaged in making it succeed

Mark the current level (C) and the desired level (D) for each stakeholder. The gap is your engagement work.

Python Engagement gap analysis

Press Run (or Ctrl + Enter) to see the result here.

Program input ยท what you'd type while the program runs

Type the answers before you press Run, one per line. Each time the program reads a line (with input()), it gets the next line from this box.

Engaging well

  • Understand interests before positions. Legal says "no"; the interest may be "protect the company from fines". Address the interest and the position softens.
  • Match the channel to the stakeholder (see communication management).
  • Involve them early. People support what they helped to create.
  • Give resistors a role: ask them for the risks they see.
  • No surprises. Tell powerful people bad news first and in private.
  • Track changes: a new executive, a reorganization or a competing project changes the grid overnight.

Who does what: the RACI matrix

Responsibilities among stakeholders and team members are clarified with a RACI matrix:

  • Responsible: does the work.
  • Accountable: owns the outcome and approves (exactly one per task).
  • Consulted: gives input before (two-way).
  • Informed: told after (one-way).
Python Validate a RACI matrix

Press Run (or Ctrl + Enter) to see the result here.

Program input ยท what you'd type while the program runs

Type the answers before you press Run, one per line. Each time the program reads a line (with input()), it gets the next line from this box.

The check shows the most common RACI mistake: a task with no accountable owner (or two). A single A keeps decisions from falling between chairs.

Common mistakes

  • Treating the sponsor as only a source of money; an engaged sponsor unblocks decisions.
  • Forgetting end users until training week.
  • Running a one-time analysis and never updating it.
  • Publishing the register with candid remarks about people. Keep it confidential and factual.
  • Confusing "informing" with "engaging". Sending a newsletter is not the same as listening.

Stakeholders are also sources of risks and change requests; a good relationship makes both easier to handle. Many stakeholder problems become conflicts, covered in team building and conflict.

Check your understanding

Quick check ยท 4 questions

of 4 answered You scored / 4 ยท perfect!

  1. 1. A senior executive has high power but low interest in your project. Strategy?

    High power, low interest: keep them satisfied with short, relevant updates and no surprises.
  2. 2. In a RACI matrix, how many Accountable owners should a task have?

    One A prevents decisions from being nobody's job and avoids conflicting approvals.
  3. 3. What is the stakeholder engagement gap?

    The matrix compares where stakeholders are with where the project needs them.
  4. 4. Which is the best way to handle a resistant stakeholder?

    Resistance usually has a reason; understanding and involving the person is the most effective path.

Summary

  • Stakeholders are anyone who affects or is affected by the project; find them early and keep looking.
  • Use the power-interest grid to prioritize and a register to record needs and strategies.
  • Close the gap between current and desired engagement levels.
  • RACI clarifies roles; every task needs exactly one accountable person.
  • Update the analysis at every phase.

Next: Team Building and Conflict