Production Methods: Job, Batch and Flow

Compare job, batch and flow production, see when each one fits, and use a runnable calculator to see how setup costs change the cost of each unit.

Every business has to turn inputs (materials, labor, machines, ideas) into outputs (goods or services). The part of the business that does this is called operations. The way a firm organizes its production is called its production method, and choosing the right one affects cost, speed, quality and flexibility.

In this lesson you will learn the three classic methods: job, batch and flow production. You will also see how fixed setup costs make some methods cheaper per unit when you make more items.

Job production

In job production a single, one-off product is made to meet a customer's exact wishes. Examples: a wedding dress, a bridge, a custom-built house, a portrait.

  • Each item is different, so skilled workers are usually needed.
  • Quality can be very high because the product is designed for one customer.
  • The cost per item is high and the process is slow.
  • It is easy to change the design, because nothing is produced in advance.

Batch production

In batch production a group (batch) of identical items moves through each stage together. When the batch is finished, the machines are reset to make a different batch. A bakery that bakes 200 white loaves, then 200 brown loaves, is using batch production. So is a clothing factory that cuts, sews and packs 500 jackets of one style before switching.

  • It is more flexible than flow production: you can switch products by resetting the machines.
  • Resetting costs time and money (these are the setup costs).
  • Work-in-progress (partly finished goods) can build up between stages and needs storage space.
  • The cost per item is lower than job production.

Flow production

In flow production items move continuously along a production line, and each stage adds something. It is used for very large quantities of identical or similar products: cars, bottled drinks, smartphones, breakfast cereal. Some people call this mass production when the numbers are very large.

  • Machines (automation) do much of the work, so the cost per item is low.
  • The line costs a lot to build, so it only makes sense when demand is high and steady.
  • Products are standardized: it is hard to change the design.
  • If one stage stops, the whole line stops.

Comparing the three methods

Feature Job Batch Flow
Quantity One Groups Very large
Variety Unique Some variety Little variety
Cost per unit High Medium Low
Flexibility Very high Medium Low
Capital cost Low Medium High
Typical worker skill High Medium Often lower (machine-based)
flowchart LR
  A["Job<br/>1 unique item"] --> B["Batch<br/>groups of items"] --> C["Flow<br/>continuous line"]

More volume and less variety move a business to the right.

How setup costs spread over units

Imagine a small factory that makes sports bottles in batches. Each time it switches to a new design it pays a setup cost (resetting machines, cleaning). Then each bottle costs a variable amount for plastic and labor.

The cost per bottle for a batch is:

cost per unit = (setup cost + variable cost per unit ร— batch size) / batch size

Notice that the setup cost is divided by the batch size. A bigger batch spreads the setup cost over more bottles. This is one of the main ideas behind economies of scale, which you will meet again in the growth lessons.

Python Cost per unit in a batch

Press Run (or Ctrl + Enter) to see the result here.

Program input ยท what you'd type while the program runs

Type the answers before you press Run, one per line. Each time the program reads a line (with input()), it gets the next line from this box.

The cost per bottle falls quickly at first and then levels out near the variable cost of $1.50. That is why flow production (which runs the same product all day) can be so cheap per unit, but also why it needs high demand.

Choosing a method

Ask these questions:

  1. How many do we need? One item points to job production, thousands to flow.
  2. How different must each item be? Custom designs need job or small-batch methods.
  3. How much can we invest? Flow lines need expensive machines.
  4. How fast must we respond to changes in fashion or demand? Flexible methods respond more easily.

Many firms mix methods. A car maker might use flow production for standard parts and job production for a special-edition model.

JS Suggest a production method

Press Run (or Ctrl + Enter) to see the console output here.

No output.

Check your understanding

Quick check ยท 4 questions

of 4 answered You scored / 4 ยท perfect!

  1. 1. Which production method is best for building one custom yacht?

    A one-off product built to a customer's wishes is job production.
  2. 2. What is a main disadvantage of flow production?

    Flow lines are expensive and hard to change, so they suit high, steady demand.
  3. 3. Why does the cost per unit usually fall as batch size increases?

    The fixed setup cost per batch is divided by a larger number of units.
  4. 4. A bakery bakes 200 white loaves and then 200 brown loaves. Which method is this?

    Identical items are made in groups, and the equipment is reset between groups.

Summary

  • Operations turns inputs into outputs.
  • Job production makes one-off items; batch makes groups; flow makes large quantities continuously.
  • More volume and less variety push firms toward flow production.
  • Setup costs are fixed per batch, so larger batches lower the cost per unit.
  • Real firms often combine methods.