Plan to Produce

Learn the plan-to-produce process: forecasting demand, bills of materials, material requirements planning, work orders, shop-floor reporting and product costing, with a runnable MRP example.

Manufacturers face a puzzle every week: what should we make, how much, and when, given what customers want, what is in stock and what materials arrive late? Plan to produce is the process that answers it. It runs from demand forecasting through production planning, material requirements planning (MRP) and work orders to finished goods and their costing.

This lesson explains the vocabulary, the planning logic and a working calculation.

The flow

flowchart LR
  A["Demand forecast and orders"] --> B["Master production schedule"]
  B --> C["MRP"]
  C --> D["Purchase requisitions"]
  C --> E["Planned production orders"]
  E --> F["Work orders on the shop floor"]
  F --> G["Finished goods and costing"]

MRP converts a plan for finished goods into purchasing and production proposals.

Key concepts

  • Item types: raw materials, components, sub-assemblies and finished goods.
  • Bill of materials (BOM): the recipe: which components, in what quantity, make one unit of a parent item. BOMs are multi-level: a bicycle needs a wheel, a wheel needs spokes and a rim.
  • Routing: the sequence of operations (cutting, welding, painting) with work centres and time per unit.
  • Work centre: a machine or group of workers with a known capacity.
  • Lead time: time between ordering (or starting) and having the item.
  • Safety stock: a buffer to absorb variation.
  • Lot size: the quantity ordered or produced at once.

Demand forecasting

Planning starts from sales orders (known demand) and forecasts (expected demand). A very simple forecast is a moving average. Real systems use seasonality and statistical models, but the idea is the same.

Python A moving-average forecast

Press Run (or Ctrl + Enter) to see the result here.

Program input ยท what you'd type while the program runs

Type the answers before you press Run, one per line. Each time the program reads a line (with input()), it gets the next line from this box.

BOM explosion

MRP starts by "exploding" the BOM: turning a quantity of finished goods into the quantity of every component.

Python Exploding a bill of materials

Press Run (or Ctrl + Enter) to see the result here.

Program input ยท what you'd type while the program runs

Type the answers before you press Run, one per line. Each time the program reads a line (with input()), it gets the next line from this box.

Ten bicycles require 20 wheels, hence 640 spokes. Hand calculation of this for hundreds of products is exactly why MRP exists.

Netting against stock

MRP does not blindly order the gross requirement; it subtracts what is on hand and what is already on order, then applies safety stock and lot sizes. The result is the net requirement and a planned order, dated earlier by the lead time.

Python Gross to net requirements

Press Run (or Ctrl + Enter) to see the result here.

Program input ยท what you'd type while the program runs

Type the answers before you press Run, one per line. Each time the program reads a line (with input()), it gets the next line from this box.

Work orders and shop-floor control

A production order (work order) authorises making a quantity of an item. Releasing it reserves components and issues them to the shop floor. Operators report progress and scrap per operation. When complete, a goods receipt brings finished goods into stock, and the components consumed are expensed to the product.

Common statuses: planned, released, in progress, completed, closed. Costing differences between planned and actual (material, labour, machine, overhead) are called variances and are analysed at period end.

Make-to-stock and make-to-order

  • Make to stock (MTS): produce from forecast, ship from stock. Fast delivery, risk of surplus.
  • Make to order (MTO): produce only after the order. Little surplus, longer delivery.
  • Assemble to order (ATO): keep components, final assembly after the order.
  • Engineer to order (ETO): design per customer, as in large machinery.

Production strategies

Make to stock From forecast
Assemble to order Components ready
Make to order After the order
Engineer to order Custom design

More custom means longer lead time

1 / 2

Costing a product

Standard cost = materials + labour + overhead per unit.

Python Product cost roll-up

Press Run (or Ctrl + Enter) to see the result here.

Program input ยท what you'd type while the program runs

Type the answers before you press Run, one per line. Each time the program reads a line (with input()), it gets the next line from this box.

Practical issues

  • Wrong BOMs or lead times make MRP output nonsense: "garbage in, garbage out".
  • Planners must act on exception messages (reschedule, cancel, expedite).
  • Capacity must be checked too; MRP alone assumes infinite capacity.
  • Inventory accuracy (cycle counting) underpins everything; see the inventory module.

Check your understanding

Quick check ยท 4 questions

of 4 answered You scored / 4 ยท perfect!

  1. 1. What is a bill of materials?

    A BOM is the recipe of a product, often multi-level.
  2. 2. MRP converts

    MRP explodes BOMs, nets stock and creates planned orders.
  3. 3. Which is NOT part of netting in MRP?

    Netting uses gross requirement, stock, open orders and safety stock.
  4. 4. In make-to-order, production starts

    Make-to-order waits for the order, avoiding surplus at the cost of longer lead time.

Summary

  • Plan to produce covers forecast, schedule, MRP, work orders and costing.
  • BOMs and routings describe what and how to make; MRP explodes and nets requirements.
  • Work orders reserve, issue and receive materials and report progress.
  • Strategy (MTS, ATO, MTO, ETO) trades delivery speed against inventory risk.
  • Data accuracy decides the quality of the plan.